Daily Production Calculator

Daily target per line and days needed to finish an order.

  • Runs locally
  • PDF report
  • Mobile ready
Plan
pcs
lines
operators
hrs/day
min
%

Live result

Checking your plan…

Your calculations are performed locally in your browser. Nothing you type is uploaded.

Quick answer

How do I set a daily production target?

Target = operators × hours × 60 × planned efficiency ÷ SMV.

Hourly / line = Operators × 60 × Efficiency% ÷ SMV

How it works

Daily Production Calculator

Set realistic daily targets and see how many working days the order needs.

Calculate each line's daily output and divide the order quantity by the combined output.

Formula

The formula, in full

Hourly / line
Operators × 60 × Efficiency% ÷ SMV
Daily / line
Hourly × Hours
Days
Order qty ÷ (Daily / line × Lines)

Example

10,000 shirts on 2 lines

  1. 01Daily / line = 524 pcs
  2. 02Total = 1,047 pcs/day
  3. 03Days = 10 working days

Use “Load Example” above to run this example in the calculator.

Industry tip

Industry tip

“Add 2–3 days for the learning curve at the start of every new style.”

Assumptions

What this calculator assumes

  • Lines run at full efficiency from day one.

FAQ

Frequently asked questions

How do I set a daily production target?

Target = operators × hours × 60 × planned efficiency ÷ SMV.

Formula and worked example checked by the TextileSuite team on 17 October 2026. Results are planning estimates — confirm critical numbers against your own samples and lab reports.